Mark Marty
6048 S. Kenton
Street
Mobile: 970-430-0619
Englewood, CO
80111
Email: MMarty2445@aol.com
PERSONAL
ATTRIBUTES:
Established
individual with sound business experienced at multiple disciplines and
capacities in all facets of construction throughout several major cities in
the U.S. and Canada.
Exceptional
knowledge and experience in all aspects of Planning, P6 Scheduling, Project
Management, Estimation, Cost Control, Contracts and Regulatory Compliance.
Proven track
record of maintaining client relations and able to create a positive morale
with co-workers and Subcontractors throughout (PLC) Project Life Cycle
Accomplished at implementing new procedures and systems while mentoring
junior personnel
PROFESSIONAL
EXPERIENCE:
Kiewit/HSE Contractors, Denver International
Airport Infrastructure Project,
June 2013 – Current
Senior Planner/Scheduler-Heavy Civil
The Project:
This project
involves the demolition of 6 bridges and the construction of 7 new bridges,
including 1000’s of feet of MSE retaining walls. This project heavy Civil
project also includes ten arterial roadways and miles of utilities required
to support the new light-rail and 500 room Westin Hotel expansion.
Responsibilities:
-
Significant time spent on long range planning and
the integration of $100 million dollars in Change Orders issued to the
Contractor (all schedules are cost and resource loaded).
-
Solely responsible for preparation and submission
end of month schedule reporting to Parsons and The City of Denver. Monthly
progress reporting including written narratives, critical path analysis, cost
load tracking, recovery planning and 3 week look-ahead task planning. Reporting
also include monitoring submittals, material deliveries, and milestone
planning.
-
Lead the charge in identifying and recovering an
additional 200 calendar days required to complete the work. This process
involved the preparation and presentation of several Time Impact Studies
(TIA’s) which measure the effect Change Orders had against the original
planned baseline schedule.
-
Considered an expert in Enterprise P6 which
includes integration of 8 different schedules to measure the combined effect
on overall project performance and resource allocations.
-
Histograms and charting which illustrate resource
leveling, cash flow projections and peak performance indicators have also
been an integral part of the reporting process.
Mark
Marty-Page 2
Ledcor/Suncor-Fort Hills, Pipeline & Early
Phase I Infrastructure Projects, Alberta CA June 2012-June 2013
Lead Planner/Scheduler-Heavy Industrial
Project #1: 8 Kilometer, 30” pipeline from the Athabasca River to the onsite
Water Treatment and Waste Water Treatment Plants and related retention ponds.
Project #2: Construct Waste Water Treatment Plant (WWTP) and a Water Treatment
Plant (WTP) including 5 holding tanks from 50k-100k gallons, two retention
ponds and distribution/conditioning of raw natural gas let down
stations/conditioning stations on site.
Responsibilities:
-
Accomplished with advanced Enterprise P6 planning
and scheduling at all levels of a project.
-
Successfully worked with Suncor, Calgary during
pre-construction project planning to define/establish WBS (Work Breakdown
Structure) in efforts to build the project schedule ground up with an EPC
(Early Project Completion) metrics.
-
Managed (PSR) Progress Status Reports for
bi-weekly schedule submissions including percentage complete with fully
resource loaded schedules that provided support to Project/Cost Control
Department for reporting.
-
Provided innovative ideas that aided in the
determination of (EVC) Earned Value Cost for monthly cost reporting and
invoicing to the client.
-
Generated; histograms, charts, graphs, manpower
forecasting, KPI Key Performance Indicator (Milestones) by receiving data
from other Field Personnel.
-
Prepare three week look-ahead schedules, that
including work fronts by area and discipline.
-
Assist in the organization and management of the
Field Installation Work Packages (FIWP) to ensure the project objectives are
accomplished.
-
P6 Enterprise exporting/importing with advanced
Excel spreadsheets for the analysis of resource loading, leveling and
forecasting peak manpower requirements on the various work fronts.
Mark
Marty-Page 3
Heath Const/USACE-Nuclear Security Tactical
Training Center, Wyoming 2011 - 2012
P M/Scheduler-Commercial/Industrial
The Project: Design-Build nuclear training facility at the US
Army Base in Guernsey Wyoming, including Ammunitions Vaults, Infirmary, and
Security Stations with a 27,000 Classroom Facility.
Responsibilities:
-
Managed Architects/Engineers, Owners Reps. and
Regulatory Officials to ensure the plans and specifications met the program
requirements.
-
Duties included, Design Phase Progress
Submissions with a 4 phase approach, estimating, buyout, Contract
negotiations, P6 Scheduling including full cost and resource loading for (PR)
Payment requisitions.
-
Accomplished at maintaining budgets and ensuring
the project deliverables are accomplished along with meeting the Stakeholder
objectives.
-
Management of the corporate procedural manuals
including updating with a project team.
-
Fully developed ground up P6 schedules in
complete compliance with USACE guidelines. Schedules
-
Proficient with project management software
including Primavera, Expedition
and Timberline, Excel, and all Office related products.
-
Change Order negotiation and management has
always been a key attribute.
M2 Design-Builders, Arizona 2002-2010
Senior Manager/Partner-Civil
-
Hands on involvement in land acquisitions,
sub-divisions, Civil Engineering and all aspects of land planning and
developing raw land to buildable construction sites.
-
Performa preparation and analysis, Concept
Estimating, CWP & EWP Breakdowns, Subcontractor bidding, preparation of
cost control management, presentations, preserving and maintaining
Owner/Client relations through the “front end process”.
-
Review Agreements and Contract language, consult
with legal counsel and act as liaison to ensure the contract is successfully
executed between the parties.
-
Managed various projects from plat development to
performing actual Project Management duties throughout construction.
Mark
Marty-Page 4
Adolfson & Peterson Construction, CO and AZ
1993 - 2001
Senior Project
Manager/Estimator-Commercial-Institutional
-
Served as senior member of management in two
different regional offices of this well established “ENR top 50” Prime
Contractor.
-
Typically Managed two midsized projects while
bidding and pricing at least one other project per month. Project Managed
over 50 Projects during the course of employment that included several
national accounts as follows; Fairchild Development, Great West Life, Denver
Public Schools, Haahn Venture Capital.
-
Nominated for Project Manager of the Year by the
A.S.A. (American Subcontractors Association).
-
Acted as Lead Estimator for two of the largest
projects ever awarded to the Rocky Mountain Regional Division. These two
projects clearly catapulted this Division to new levels of “high rise
construction” and University projects.
OTHER
PROFESSIONAL EXPERIENCE:
-
Change Order Negotiator, Morrison Knudson Corp.,
Denver International Airport (original construction). Duration; One
year
-
Dept. Head of Estimating, Ehrlich-Rominger,
Engineers/Architects, Palo Alto, California. Duration; Three years
-
Estimator, NBBJ Group, Engineers/Architects, San
Francisco, California. Duration; Two years
EDUCATION/PROFESSIONAL
AFFILIATIONS:
M.B.A. Project
Management, Golden Gate University, San Francisco, CA
B.S. Minnesota
State University, Mankato, MN
PMP In Study,
Project Management Institute.
Oracle
Primavera P6 Certification
American
Society of Professional Estimators-Active group member and former CPE
(Certified Professional Estimator)
American
Society of Civil Engineers-Active Member